The Dubai Municipality in UAE set the record to be the largest 3d-printed structure with a standing tall of 9.5 meters and an area of 640 square meters. Apis Cor, a U.S.-based company, constructed the structure, which is the first to build specialized equipment for 3D printing on its own in the construction sector. The two-story construction was erected entirely on-site, with no additional assembly required.
阿联酋迪拜市创造了世界上最大的3d打印建筑的纪录,该建筑高9.5米,面积为640平方米。该结构由美国公司Apis Cor建造,这是建筑领域第一个自行建造3D打印专用设备的公司。两层建筑完全在现场搭建,不需要额外的组装。
The building’s base is traditional, but the walls are 3D printed, and reinforcement is “3D-printed formwork for columns manually filled with rebar and normal concrete.” The 3D Printing material utilized for this business is a gypsum-based combination created by Apis Cor and manufactured locally. Pre-cast slabs were also used for the flooring, with a local contractor adding typical windows and roofs after the walls were completed.
建筑的基础是传统的,但墙壁是3D打印的,而钢筋是“手工填充钢筋和普通混凝土的柱的3D打印模板”。该业务使用的3D打印材料是由api Cor创建的石膏基组合,并在当地制造。预制板也用于地板,当地承包商在墙壁完成后添加了典型的窗户和屋顶。
The printing was completed on the site to show that the technology could withstand a hostile environment with no humidity or temperature control. Apis Cor’s unique 3D-printing machine was moved around the site using a crane to re-position. The overall size of the structure is 640 square meters, which is “bigger than the printing area accessible when the Apis Cor’s 3D printer is stationary.”
在现场完成了打印,以表明该技术可以承受没有湿度或温度控制的恶劣环境。api Cor独特的3d打印机使用起重机在场地周围移动以重新定位。该结构的整体尺寸为640平方米,“比api Cor的3D打印机固定时的打印面积更大。”
“Construction 3D printing technology is only at the early stages of development. We do extensive R&D work to make the technology available for mass use. We are thankful for the opportunity to collaborate with Dubai Municipality. The project gave us unique knowledge and invaluable experience that will help us improve our technology and develop a new version of our 3D printer. The improved version will be more reliable and time-efficient (twice as fast). Moreover, during the project, we tested and improved our own-developed 3D mixture. This project is a huge step forward in the concrete 3D printing industry.” Nikita Cheniuntai, CEO&Founder of Apis Cor.
建筑3D打印技术还只是处于发展的早期阶段。我们做了大量的研发工作,使这项技术可以大规模使用。我们非常感谢有机会与迪拜市政府合作。这个项目给了我们独特的知识和宝贵的经验,将帮助我们提高我们的技术和开发我们的新版本的3D打印机。改进后的版本将更加可靠和省时(速度是原来的两倍)。此外,在项目过程中,我们对自己开发的3D混合材料进行了测试和改进。该项目是混凝土3D打印行业向前迈出的一大步。Nikita Cheniuntai, Apis Cor的创始人。
The Dubai Municipality has won the UAE Ideas Award organized by the Dubai Quality Group under the slogan, “Nothing is Impossible,” for the category of “Innovation in the field of inventions.”
迪拜市以“没有什么是不可能的”为口号,在“发明领域的革新”领域获得了由迪拜质量集团主办的“阿联酋创意奖”。
By 2030, the Dubai government hopes to have used 3D printing technology to construct 25% of its structures. The initiative extends the role of 3D printing technology in decreasing construction costs by 50-70 percent and labor expenses by 50-80 percent, as well as reducing construction waste by up to 60 percent. It has a favorable impact on the sector’s economic return and helps to achieve environmental and resource sustainability.
到2030年,迪拜政府希望使用3D打印技术建造25%的建筑。该计划扩大了3D打印技术的作用,将建筑成本降低50% - 70%,劳动力成本降低50% - 80%,并将建筑垃圾减少高达60%。这对该行业的经济回报产生了有利的影响,并有助于实现环境和资源的可持续性。
Project info:
Building: Dubai Municipality
Location: Dubai, UAE
Structure type: Hybrid ( conventional base + 3D-printed walls)
Building use: Administrative building
Designer: Yves Behar
Constructor: Apis Cor,
Area: 640 square meters
Photography: Apis Cor
(责任编辑:何雯丽)
延伸阅读:
智能建造技术技能人才培养路径优化研究 李德令:医疗建筑的智能建造与智慧运维 智慧建造工厂助力新型建筑工业化(1) 凡本网注明“来源:预制建筑网”的所有资料版权均为预制建筑网独家所有,任何媒体、网站或个人在转载使用时必须注明来源“预制建筑网”,违反者本网将依法追究责任。 (2) 本网转载并注明其他来源的稿件,是本着为读者传递更多信息之目的,并不意味着赞同其观点或证实其内容的真实性,请读者仅作参考,并请自行核实相关内容。其他媒体、网站或个人从本网转载使用时,必须保留本网注明的稿件来源,禁止擅自篡改稿件来源,并自负版权等法律责任,违反者本网也将依法追究责任。 (3) 如本网转载稿涉及版权等问题,请作者一周内书面来函联系。